Friday, November 18, 2011

Closing Timeline

The builders got us a timeline but they still haven't told us a closing date. From what I can see I am thinking/hoping (based on our current choices) we are closing 12.22.11. Yes a day or two before Christmas. We emailed the bank and they are thinking we will be closing any where between 12.26.11 and 12.29.11 and the banker man is not worried though he isn't the one having to close, move to be out of an apartment by 01.01.12 and work full time jobs. Really hoping we close on 12.22.11 as Brian and I cannot take time off work between 12.26.11-12.29.11. I really shouldn't be taking 12.22.11 off but I am going to have to. Do not want to even think about what happens if the house gets delayed so we don't close until after the New Year.

Mom and I have come up with a plan so that we can come home for Christmas and still move in without taking time off. The ideal solution is that we close the 22nd, leave for Christmas and Mom comes back with us on the 26th and stays with the movers on the 27th while Brian and I are at work. If we don't close the 22nd but close the 26th or so she will just fly down for the day to help close. We may have to enlist help from friends around but that is the current goal and I feel better about it.

And for your information, here is the closing timeline. Feel free to let us know when you think we are closing based on this.

11-15 thru 11-21Sheetrock

11-17Install water/sewer

11-21Pour flatwork

11-22Deliver and install cabinets first thing - Deliver interior trim before AM - Start interior trim after 12

11-23Install interior trim

11-25 thru 11-30paint

12-1Install tile - Install vinyl flooring

12-2Grout tile - Install vinyl flooring - Cover flooring in the PM - Deliver first appliances - Install marble walls and shelf in the PM

12-5Plumbing trim out - HVAC trim out - Measure for shower door

12-6Electric trim out, make sure you have enough people to have ready in one day (all ready for final insp.) - Blow attic insulation - Call for final insp.

12-7Final insp. - Install mirrors and shelving - Install garage door

12-8Set power meter

12-9Install wood flooring - Landscaping - Deliver shoe, locks, and hardware - Install screening

12-12Cover wood flooring first thing - Install shoe and hardware - Install cabinet shoe and final adjustments, check caulking - Install shower door - Landscape - Deliver second appliances, Deliver window screens

12-13Final clean and install screens

12-14Pressure wash - Final paint prior to carpet, Make up punch list

12-15Punch list complete

12-16Install gutters - Install carpet - Call for CO insp. - Deliver Hurricane panels

12-19CO insp. - Quality walk for corrections

12-20Quality corrections

12-21Touch up clean

12-22Home owner walk